CRQ McClellan-Palomar Airport

Runway 24 EMAS improvement

Active opportunity CIP Project type: New installation
8.0
Details
Lifecycle
Active opportunity
Sources point to current or upcoming economic activity right now - funding, procurement, design or construction.
Status
CIP
Project type
New installation
Confidence
Planning year
2027
Procurement year
Runway
6/24
Likely supplier
Runway Safe
Reasoning
Caltrans CIP identifies EMAS project; not yet awarded.
Source

California Aeronautics Capital Improvement Plan

Caltrans · CIP

Last verified source: 2025-06-01

Open source →
Details from the source Free text (cost, date, etc.) without its own database fields

Programmed EMAS project for Runway 24.

Economics
Total project budget
$25,000,000
Estimated EMAS share